Parking Lot Expansion Phase 2
      Square Feet:
      Project Budget:
      Construction Duration:
      Funding Source:
22,600
$1.1 Million
Summer 2006 - Summer 2006
Proposition R
 
 
      Scope/Summary:
 
      Phase 2A of this project added 291 parking spaces to Parking Lot 5 across from the One-Stop
      Student Services Center. The project was critical as construction of the Communication Arts
      Building removed more than 140 parking spaces from Parking Lots 1, 2, and 3.
 
      Project Team:
  • Engineer: Nolte Associates, Inc.
  • General Contractor: SRM Contracting and Paving
  • Program Manager: Joe Minner, Gafcon, Inc.
  • Senior Project Manager: Erik Reuter, Gafcon, Inc.
  • Project Manager: Aaron Golde, Gafcon, Inc.
  • Proposition R & V Program Manager: Gafcon, Inc.

    

      Phase 2B added 16 accessible parking spaces and 36 staff parking spaces with the paving of the
      sand volleyball court between the track and gymnasium. This project provides more parking near
      the center of campus.

      Project Team:
  • Engineer: RBF Consulting
  • General Contractor: SRM Contracting and Paving
  • Program Manager: Joe Minner, Gafcon, Inc.
  • Senior Project Manager: Erik Reuter, Gafcon, Inc.
  • Project Manager: Aaron Golde, Gafcon, Inc.
  • Proposition R & V Program Manager: Gafcon, Inc