You may be trying to access this site from a secured browser on the server. Please enable scripts and reload this page.
Turn on more accessible mode
Turn off more accessible mode
Skip Ribbon Commands
Skip to main content
GCCCD Props RV
About
About
Citizens’ Bond Oversight Committee
Sustainability
GCCCD
Community Benefit Agreement and Project Labor Agreement
Projects
Currently selected
GCCCD Projects
Grossmont College
Cuyamaca College
Districtwide
Project Reports Library
Bids
Current Bids & Schedules
Archived Bids
Resources
Design & Construction Standards
Professional Services Firm Directory
Labor Compliance
Contractor Outreach
News & Publications
Props R & V in the News
Program Publications
Griffin Center/Student Services Administration
GCCCD Props RV
>
Projects
>
Griffin Center/Student Services Administration
Libraries
Program Resources
Program Schedule
Facilities Master Plan
Facilities Funding Plan
Design Guidelines & Standards
Prop R Projects
Digital Arts/Sculpture Complex
Exercise Science and Wellness Complex
Griffin Center/Student Services Administration
Health Sciences Complex
Learning and Technology Resource Center
Life Safety Entrance Road
Parking Expansion
Science Building
Prop V Projects
Arts & Communication Complex - Phase 1
Prop V Projects Overview
Science, Math and Career Tech Complex - Phase 1
Districtwide Projects
Year 1 Lighting Fixtures & Controls Update
Year 2 Lighting & HVAC Upgrade
Infrastructure Assessment
All Site Content
Page Content
Library
Sustainability
Campus Map
Square Feet:
Project Budget:
Construction Duration:
Funding Source:
83
,966 Combined
$38.5 Million
Summer 2010 - Winter 2011
Proposition R
Scope/Summary:
Prominent as a gateway building, the
Student & Administrative Services Building
provides a
welcoming entry into the heart of the campus. The project featured a remodeling and expansion
that enclosed the interior courtyard and breezeway areas. An expanded one-stop center
improved access to student services including admissions and records, assessment, counseling,
transfer center, international students, veterans affairs, and financial aid. The complex also
houses administrative and support services offices including cashier, business office, instructional
operations, deans’ offices, and college and community relations.
The
Griffin Center
was renovated to improve the dining and food service areas, and upgraded to
meet current accessibility and code requirements. A partial second story was added. The building
accommodates Associated Students, dining areas, culinary arts, student health services, EOPS,
career center, job placement, lounge/game areas, a quiet lounge, adjunct faculty offices, adult re-
entry, disabled student programs and services, Griffin Gate/Governing Board meeting room,
student affairs office, and a student club room.
Project Team:
Architect:
Architects Mosher Drew Watson Ferguson
Construction Manager:
Rudolph & Sletten
Program Manager:
Jim Davies, Gafcon, Inc.
Senior Project Manager:
Jim Davies, Gafcon, Inc.
Project Manager:
Ken Emmons
, Gafcon, Inc. & Tom Webb, Gafcon, Inc.
Proposition R & V Program Manager:
Gafcon, Inc.